Connector Road - Construction Program and General Information
________________________________________________________________________________________
The content of this page is currently under review, for more information please contact Oliver Pfueller on 8375 6607 during office hours or by email Oliver.Pfueller@marion.sa.gov.au
LATEST UPDATE ON CONSTRUCTION
The City of Marion provides below the construction program for the Connector Road. The program includes all works undertaken on the road and adjacent intersections as well as landscaping works. Built Environs as selected tenderer has endorsed this program together with Maunsell Australia as Council's project manager.
Built Environs’ Connector Consultation phone no is 0418 941 240.
| Construction Program |
 |
Lonsdale Intersections
- Connector Road
- Ramrod Ave | Feb 07 – Aug 08
Nov 08 |
- Speed restrictions and lane narrowing
- Some night work with speed and lane diversions
|
Connector West
(of Lonsdale Road – adjacent Shakes Cres.) | Dec 07 – Aug 08
|
- Excavation – continuous truck movement on site - completed
- Impact rolling deep in cutting - completed
- Backfilling - continuous truck movement within site - completed
- Drainage kerbing and sealing
|
| Gledsdale/Quailo/Zwerner Intersection | Dec 07 – Apr 08
completed |
- Roadworks - completed
- Finishing works include footpaths and lights - completed
|
| Connector East (Lonsdale to Berrima) | Dec 07 – Oct 08 |
- Construction traffic via Lonsdale and Lander Roads
- Maximum 3 to 4 truck deliveries per hour
|
| Berrima Roundabout | Aug 08 – Sept 08 |
- Short duration closure - dates to be advised
- Speed restrictions and some “stop/go”
|
| Lander Ave/Lander Rd Roundabout | Sept 08 – Oct 08 |
- Access maintained throughout
- Speed restrictions and some “stop/go”
|
| Completion | 4th Quarter 2008 |
Please see below for more detailed information on the construction works.
| Construction General |
- Work on 5 days/week (sometimes 6)
- Hours 7am to 5pm (7am – 1pm Saturday)
- Some night work on Lonsdale Road
- Construction traffic minimised on local streets
- As much as possible will be directly to and from Lonsdale subject to the conditions and requirements of DTEI
- Some traffic restrictions – will be advised in advance (letterbox drops and signs)
- Dust management
- Regular community meetings
|
|