Glandore Oval, Glandore | Works from March to May 2019

Posted:
Thursday 07 Mar 2019
Please note the content of this news item is over six months old and may no longer be current.
Glandore Oval Works March To May 2019

Works on the southwestern corner of Glandore Oval will commence in March 2019.

The works to be undertaken:

  • Refurbishment of the 2 courts adjacent to South Road to be converted into multiuse courts (tennis/netball).
  • New internal and external fencing.
  • Demolition of clubhouse.
  • Installation of multi-use play equipment including basketball and soccer nets and a mini bike track.
  • Additional fencing for existing playground area.
  • Landscaping.

The remainder of the site will remain accessible, including the playground and picnic facilities.

We anticipate the work will be completed in May 2019.