Work is continuing on the upgrade of Heron Way Reserve, including the construction of a new playground.
In the past couple of months paths have been laid and retaining walls constructed. Sheltered picnic facilities are starting to take shape with shelters, tables and BBQs installed.
Poles for the shade sails over the playground are in place, ready for the sails to be installed just before the reserve re-opens.
Landscaping of Heron Way is complete. Landscaping around the playground will be undertaken in approximately April/May 2019 (next planting season).
Installation of playground equipment has begun including the 5-way swings and slide.
It is anticipated that the first stage of works incorporating the playground will be completed by November 2018. It is anticipated stormwater and landscaping works will commence in February/March 2019 following Australia Day.